PART I - Project Cash Flow Analysis Analyze the cash inflows and outflows of the project shown below following the Example Project Cash Flow Analysis

PART I - Project Cash Flow Analysis

Analyze the cash inflows and outflows of the project shown below following the Example Project Cash Flow Analysis posted in Module 1 lecture resources. What is the contractor's expected profit in this project?

Work Type Month 1 Month 2 Month 3 Month 4 Month 5
Move in 1,750
Survey 800
Trench 2,300 5,250
Lay Pipe (Sub) 2,250
Concrete (Sub) 700 700
Backfill 500
Move out 350
Fix Valves 700
Put Valves 700
Test 1,000
  • The dollar values shown in the table above are in thousands
  • The contractor is subcontracting the pipe laying and concreting works only.
  • The owner and engineer need one month to review, approve, and authorize progress payment upon receipt of the invoice from the contractor.
  • The contractor will pay the subcontractors the same month he collects his payment from the owner.
  • The contractor's total indirect costs are $1,800,000 and the markup is 3%.
  • The retainage percent is 10%.
  • Use an interest rate of 1.5%.

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Succeeding in Business with Microsoft Excel 2013 A Problem Solving Approach

Authors: Debra Gross, Frank Akaiwa, Karleen Nordquist

1st edition

978-1285099149, 9781285963969, 1285099141, 1285963962, 978-1285715346

More Books

Students also viewed these Finance questions

Question

CL I P COL Astro- L(1-cas0) Lsing *A=2 L sin(0/2)

Answered: 1 week ago