Question

1 Approved Answer

Part III: MRP The company has a metal - forming plant in Dongguan. It makes a wide variety of commercial and industrial electrical products, used

image text in transcribed
Part III: MRP
The company has a metal - forming plant in Dongguan. It makes a wide variety of commercial and
industrial electrical products, used to disconnect and protect wiring systems including computer
systems. They have an MRP II system in place and use the system to release work orders to
manufacturing and recommended quantities to purchasing.
Two of the products manufactured at plant are standard metal enclosures for electrical disconnects
that are made from metal sheet, which comes in 2 , 0 0 0 - kg rolls. Previous work in standardizing their
products has lead to the ability to make both final products ( A and B ) ?entirely from one raw material
( X ) . ?There are some components ( W , ?Z and Y ) ?that go into the final products. These are
manufactured in separate areas and are made from raw material ( X ) . ?All information on the final
products, components, and raw material are given in typical MRP format. All the information is
stated in the attached "item master files", "where - used files", and "master production schedules".
You are the planner in charge of producing the A and B plus all the components and the raw material.
( Note that part Y experiences some independent demand. It is a panel used in joining one or more
enclosures together by the installer and there is a small continuous demand for this part. )
Requirements:
Using the MRP sheet provided, complete the planning sheets for all the parts according to the steps
below:
Complete the Master Schedules for Products A and B . ( Master Production Plan is made in
accordance to demand / forecast ) . ?The results in this part will be shown in the answers of part 3 .
Using the information from the "where - used files", construct "product structure trees" for the
final products. For each product enter the low - level code on the respective item master file.
Basing on the information from the master schedule, complete the MRP worksheets for each of
the components and for the raw material. Be sure to include all of the information from the "item
master files .
image text in transcribed

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Project Management Planning And Control Techniques

Authors: Rory Burke

3rd Edition

047198762X, 9780471987628

More Books

Students also viewed these General Management questions