Question
Pavel agreed to build a yacht for Dixie. The yacht was to be delivered to Dixie on July 15 and Pavel was to be paid
Pavel agreed to build a yacht for Dixie. The yacht was to be delivered to Dixie on July 15 and Pavel was to be paid the total price of $100 000 on the same day. Which of the following statements is TRUE?
- If Pavel delivers the yacht on July 15, but has not stenciled the name Sea Bird on the back of the boat as he had promised to do, Dixie is certainly entitled to refuse delivery and withhold the purchase price.
2.If Pavel completes construction of a yacht on July 1, only to see it destroyed by a hurricane the next day, the contract may bedischarged on the basis of frustrationif Pavel does not have enough time to build another yacht for Dixie by July 15.
3.If Pavel delivers the yacht half-built, together with the materials that will be required to actually complete construction of the boat, he is entitled to have the contract discharged on the basis of "substantial performance" as long as he compensates Dixie for the price that she will have to pay to have another person finish the project.
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started