Question
(Payback period, NPV, PI, and IRR calculations) You are considering a project with an initial cash outlay of $90,000 and expected free cash flows of
(Payback
period, NPV, PI, and IRR
calculations)
You are considering a project with an initial cash outlay of
$90,000
and expected free cash flows of
$26,000
at the end of each year for
7
years. The required rate of return for this project is
9
percent.
a. What is the project's payback period?
b. What is the project's
NPV?
c. What is the project's
PI?
d. What is the project's
IRR?
a. The project's payback period is
3.463.46
years.(Round to two decimal places.) b. The project's NPV is
$40,856.7740,856.77.
(Round to the nearest cent.)c. The the project's PI is
1.451.45.
(Round to three decimal places.)d. The project's IRR is
2121%.
(Round to two decimal places.)
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started