Pendennis plc had the following budget and actual figures for Product ZN6 during April: Budget Actual Output 2,200 units 2,500 units Sales revenue 176,000 205,000

Pendennis plc had the following budget and actual figures for Product ZN6 during April:

Budget

Actual

Output

2,200

units

2,500

units

Sales revenue

176,000

205,000

Raw materials

(77,000)

22,000 metres

(98,800)

28,000 metres

Labour

(66,000)

11,000 hours

(65,000)

13,000 hours

Fixed overheads

(24,200)

(21,400)

Profit

8,800

19,800

What is the materials price variance for Product ZN6 for the month of April?

A.

800

adverse

B.

714

favourable

C.

800

favourable

D.

714

adverse

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Practical Guide To Auditing SAP Systems

Authors: Martin Metz, Sebastian Mayer

1st Edition

3960126409, 978-3960126409

More Books

Students also viewed these Accounting questions