Penobscot Nuclear has a contract to build a state of the art breeder reactor in Maine. This will be the first reactor built in the
Penobscot Nuclear has a contract to build a state of the art breeder reactor in Maine. This will be the first reactor built in the U.S. in many years and the only breeder reactor in the country. The contract cost is $1 billion and is expected to take 4 years to complete.
Here are some relevant facts (all numbers in the table are in millions):
Contract price: $1,000 Million
2016 | 2017 | 2018 | 2019 | |
construction cost incurred in the current year: | $100 | $300 | $400 | $180 |
Estimated cost to complete the contract at the end of the year: | $700 | $400 | $450 | $0 |
Billing on the contract in the current year | $120 | $340 | $400 | $140 |
Dollars collected on billings in the current year | $80 | $360 | $320 | $240 |
Complete the required jorunal entries for each year using the percentage-of-completion contract method. also show the relevant balance sheet and income statement presentation, and complete T-accounts for construction-in-progress and billings-on-contract accounts.
Penobscot Nuclear Balance sheet December 31, 2015
Cash $800
Retained Earnings $ 300 Common Stock 500 Total Equity $ 800
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started