Peony Company Peony Company has developed a static budget for the month of August, which is based on 9,000 direct labour hours. During the quarter,

Peony Company

Peony Company has developed a static budget for the month of August, which is based on 9,000 direct labour hours. During the quarter, the actual activity was 10,000 direct labour hours. Data for August are summarized as follows:

Static Budget (9,000 hours)

Actual Costs (10,000 hours)
Direct labour $117,000 $120,000
Power (variable cost) 45,000 50,000
Salary of plant supervisor 5,000 5,000
TOTAL $167,000 $175,000

Refer to Peony Company. What can be concluded when comparing the static budget to the actual costs?

The salary of the plant supervisor is fixed.
Immediate action is needed to reduce costs.
The plant manager was clearly not efficient.
The manager spent more than should have been spent.

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Principles of Accounting

Authors: Needles, Powers, crosson

11th Edition

1439037744, 978-1133626985, 978-1439037744

More Books

Students also viewed these Accounting questions

Question

What are the interactions between quality control and purchasing?

Answered: 1 week ago