Question
1 Approved Answer
Percentage of completion of a long-term contract cannot be determined by: Dividing billings to date by total expected billings. Dividing costs incurred to date by
Percentage of completion of a long-term contract cannot be determined by: Dividing billings to date by total expected billings. Dividing costs incurred to date by estimated total costs. Dividing number of units produced by total production number specified in contract. Dividing tonnage of raw materials used by estimated total tonnage of raw materials required