Perfect Perambulators uses a subcontractor to provide handles. They need 24 handles a day, and the lead time for ordering handles is 4 days. After
Perfect Perambulators uses a subcontractor to provide handles. They need 24 handles a day, and the lead time for ordering handles is 4 days. After negotiations, the subcontractor is required to reduce the lead time to 1.5 days. By how much does this lower the reorder point