Question
1 Approved Answer
(PERT project scheduling) Predecessors Optimistic Time (a) Most Likely Time (m) Pessimistic Time (b) A 0.5 1 1.5 B A 2 4 5 C A
(PERT project scheduling) Predecessors Optimistic Time (a) Most Likely Time (m) Pessimistic Time (b) A 0.5 1 1.5 B A 2 4 5 C A 2 3 6 D A 6 7 8 E B 4 6 7 F C, D 1 2 2.5 G E, F 6 7 9 H D 6 9 11 I G, H 2 4 6 EXPECTED ACTIVITY What are the expected time(E) and the variance of expected time (2) for each activity? Identify the critical path and determine the expected time to complete the project (Ecp). Compute the variance of the critical path duration (cp2). Whatistheprobabilitythattheprojectwillbecompletedin24daysorless? What is the probability that the project will be completed in 21 days or less? What is the probability that the project will be completed in 20 days or more? VARIANCE
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started