Question

1 Approved Answer

PERT refers to Program Evaluation and Review Technique, which was developed in the 1950s to better understand how variability in the individual activity durations impacts

PERT refers to Program Evaluation and Review Technique, which was developed in the 1950s to better understand how variability in the individual activity durations impacts the entire project schedule.

a. True
b. False

Typically, expedited costs are preferred over regular costs.

a. True
b. False

If the project manager changes an activity on the critical path to start at a later date, then the whole project will end at a later date.

a. True
b. False

Estimate Activity Resources focuses exclusively upon the identification of the number of human resources required to perform each scheduled activity.

a. True

b. False

Which of these is NOT an issue to be considered when selecting team members?

a. stages of team development
b. virtual teams
c. cross functional teams
d. co-located teams

cross-functional

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Business Management

Authors: Lokyie Lomine, Martin Mwenda Muchena, Robert Pierce

1st Edition

1382016832, 978-1382016834

More Books

Students also viewed these General Management questions