Pharoah Construction entered into a contract to construct a bridge for a contract price of $2.85 million. Construction began in 2019 and was completed in

Pharoah Construction entered into a contract to construct a bridge for a contract price of $2.85 million. Construction began in 2019 and was completed in 2021. Below are the details of the transactions related to the contract:

2019 2020 2021
Costs incurred during the year $657,000 $816,000 $723,900
Estimated costs to complete 1,624,250 527,000 0

Calculate the revenue, expenses and gross profit to be recognized each year using the percentage-of-completion method. (Round the percentage completion to 2 decimal places, e.g. 52.75% and other answers to 0 decimal places, e.g. 1,525.)

2019 2020 2021
Revenue $ $ $
Expenses
Gross Profit $ $ $

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Accounting Concepts And Applications

Authors: K. Fred Skousen, W. Steve Albrecht, James D. Stice, Earl K. Stice

7th Edition

0538876247, 978-0538876247

More Books

Students also viewed these Accounting questions

Question

=+2. Explain the interactions in the newspaper and magazine market!

Answered: 1 week ago