Question
1 Approved Answer
Pharoah, Inc. began work on a $7,579,000 contract in 2020 to construct an office building. During 2020, Pharoah, Inc. incurred costs of $1,865,850, billed its
Pharoah, Inc. began work on a $7,579,000 contract in 2020 to construct an office building. During 2020, Pharoah, Inc. incurred costs of $1,865,850, billed its customers for $1,081,000, and collected $1,022,000. At December 31, 2020, the estimated additional costs to complete the project total $3,465,150. Prepare Pharoahs 2020 journal entries using the percentage-of-completion method.
Account Titles and Explanation | Debit | Credit |
---|---|---|
Construction in Process | 1865850 | |
1865850 | ||
(To record costs incurred.) | ||
Accounts Receivable | 1081000 | |
Billings on Construction in Process | 1081000 | |
(To record billings.) | ||
Cash | 1022000 | |
Accounts Receivable | 1022000 | |
(To record collections.) | ||
Construction in Process | ||
Construction Expenses | 1865850 | |
Revenue from Long-Term Contracts | ||
(To recognize revenue.) | ||
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started