Question
Pickle Company has contracted to build for the city of Charleston a new school.The estimated cost is $6,000,000 and the contract price is $9,000,000.The school
Pickle Company has contracted to build for the city of Charleston a new school.The estimated cost is $6,000,000 and the contract price is $9,000,000.The school took three years to complete as follows:
2020 2021 2022
Costs to Date $1.500,000 $4,000,000 $6,200,000
Costs to Complete $4,500,000 $2,200,000 $0
Amounts Billed to Date $1,300,000 $5,800,000 $9,000,000
Collections to Date $1,300,000 $4,300,000 $9,000,000
a) Determine using the percentage of completion method the gross profit to be recognized for:
2020 2021 2022
b) Determine using the completed contract method the gross profit to be recognized for:
2020 2021 2022
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started