Pickle Company has contracted to build for the city of Charleston a new school. The estimated cost is $6,000,000 and the contract price is $10,000,000.

Pickle Company has contracted to build for the city of Charleston a new school. The estimated cost is $6,000,000
and the contract price is $10,000,000. The school took three years to complete as follows:
2020 2021 2022
Costs to Date $1,500,000 $4,000,000 $6,200,000
Costs to Complete $4,500,000 $2,200,000 $0
Amounts Billed to Date $2,300,000 $5,800,000 $10,000,000
Collections to Date $1,300,000 $5,300,000 $10,000,000
Determine using the percentage of completion method the gross profit to be recognized for:
2020 2021 2022

B.

b Determine using the completed contract method the gross profit to be recognized for :
2020 2021 2022

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Research Methods In Accounting

Authors: Malcolm Smith

5th Edition

1526490676, 978-1526490674

More Books

Students also viewed these Accounting questions

Question

=+d. Purchaser: buys the item.

Answered: 1 week ago