Pina Construction Company began work on a $420,500 construction contract in 2020. During 2020, Pina incurred costs of $299,000, billed its customer for $202,000, and

Pina Construction Company began work on a $420,500 construction contract in 2020. During 2020, Pina incurred costs of $299,000,

billed its customer for $202,000, and collected $177,000. At December 31, 2020, the estimated additional costs to complete the

project total $151,030.

(b)

Prepare Pina's journal entry to record profit or loss, if any, using (a) the percentage-of-completion method and (b) the completed

contract method. (Credit account titles are automatically indented when amount is entered. Do not indent manually. If no entry is required,

select "No entry" for the account titles and enter O for the amounts. Round answers to O decimal places, e.g. 5,275.)

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Cornerstones of Cost Management

Authors: Don R. Hansen, Maryanne M. Mowen

2nd edition

1111824401, 978-1111824402

More Books

Students also viewed these Accounting questions