Question

1 Approved Answer

Pina Construction Company uses the percentage-of-completion method of accounting. In 2020, Pina began work under contract #E2-D2, which provided for a contract price of $2,243,000.

Pina Construction Company uses the percentage-of-completion method of accounting. In 2020, Pina began work under contract #E2-D2, which provided for a contract price of $2,243,000. Other details follow:

2020

2021

Costs incurred during the year $658,560 $1,434,000
Estimated costs to complete, as of December 31 909,440 0
Billings during the year 417,000 2,243,000
Collections during the year 345,000 1,511,000

(a)

What portion of the total contract price would be recognized as revenue in 2020? In 2021?
Revenue recognized in 2020 $

Revenue recognized in 2021

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access with AI-Powered Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Students also viewed these Accounting questions