Question
Pinetree Builders has the following data for its Rolling Hills Construction Project. The contract price of the project is $18,000,000. Complete the following table with
Pinetree Builders has the following data for its Rolling Hills Construction Project. The contract price of the project is $18,000,000. Complete the following table with the required information using the percentage of completion method.
| 2016 | 2017 | 2018 |
Costs incurred to date | $4,500,000 | $10,500,000 | $15,500,000 |
Estimated costs to complete | 10,500,000 | 2,625,000 |
|
Billings during the year | 6,600,000 | 8,400,000 | 3,000,000 |
Cash collections during the year | 6,000,000 | 6,000,000 | 6,000,000 |
Estimated total costs |
|
|
|
Estimated total profit |
|
|
|
Percentage of Completion |
|
|
|
Revenue Recognized in each year |
|
|
|
Profit recognized in each year |
|
|
|
Current Asset |
|
|
|
Current Liabilities |
|
|
|
Required
1. Enter the appropriate amounts in the shaded cells above.
2. Prepare the required journal entries for 2016, 2017 and 2018.
Date | Accounts Title and Explanation | Ref. | Debit | Credit |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started