Pinnacle Corp, budgeted $231,070 of overhead cost for the current year. Actual overhead costs for the year were $224,270. Pinnacle's plantwide allocation base, machine hours,
Pinnacle Corp, budgeted $231,070 of overhead cost for the current year. Actual overhead costs for the year were $224,270. Pinnacle's plantwide allocation base, machine hours, was budgeted at 46,310 hours. Actual machine hours were 40,470. A total of 106,670 units was budgeted to be produced and 98,000 units were actually produced. Pinnacle's plantwide factory overhead rate for the current year is: a $4.99 per machine hour b. $2.17 per machine hour c. $4.84 per machine hour d. $2.10 per machine hour
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started