Piper Corporation's flexible budget cost formula for maintenance, a mixed cost, is $3,500 + $0.3X, where X is machine-hours. The company reported a $250 favorable
Piper Corporation's flexible budget cost formula for maintenance, a mixed cost, is $3,500 + $0.3X, where X is machine-hours. The company reported a $250 favorable spending variance for maintance in February. The company had originally planned to work for 10,000 machine hours but ended up working for 15,000 machine-hours during the month. What was the actual costs incurred for maintenance in February? 8:18 Multiple Choice