PizzaTime Restaurants is building a new pizza place and needs to determine how big to make the various parts of its facility. It wants to

PizzaTime Restaurants is building a new pizza place and needs to determine how big to make the various parts of its facility. It wants to be able to accommodate a maximum of 260 customers per hour at its peak times. PizzaTime has collected the following information: the average time to place and receive an order is 0.95 minutes, 20 percent of the customers have cars and require parking spots, and the average length of time at the restaurant is 30 minutes per customer. Assume a capacity cushion of 20 percent.
Find the number of cash registers required. (assume an average of 4 customers per group)
Find the number of parking spaces needed.
Find the number of seats/tables needed. (assume 4 seats per table).

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Organization Theory And Public Management

Authors: Jonathan R. Tompkins

1st Edition

053417468X, 978-0534174682

More Books

Students also viewed these General Management questions