PJM650 PROJECT SCENARIO McEvers Middle School's principal, Jacqueline Davis, has received grant approval and has been awarded 75 new HP Envy 15-ep1010nr laptops for their

PJM650 PROJECT SCENARIO

McEvers Middle School's principal, Jacqueline Davis, has received grant approval and has been awarded 75 new HP Envy 15-ep1010nr laptops for their three computer labs. The following criteria must be met:

  • Laptops will accommodate 25 students per class.
  • Laptops must have monitor connection to at least 10 existing monitors.
  • Students will be able to checkout laptops through the school lab checkout system with approval.
  • Laptops will need to be Internet-accessible and equipped with the following browsers:
    • MS Edge
    • Google Chrome
    • Mozilla Firefox
  • The laptop software must also include Microsoft 365 with the following:
    • Word
    • Excel
    • PowerPoint
    • MS Teams
    • OneNote
    • Outlook
  • All student laptops will require comprehensive security protection and configured for Internet restrictions.
  • All laptops must have connectivity to the school district network and server infrastructure.
  • All software and laptop configurations must be installed and tested prior to project implementation.
  • The project is scheduled to be started 5 days after delivery and must be completed within 5 weeks.

Project Manager Responsibilities

As the project manager, you will be responsible for leading the team of three other resource infrastructure technicians, as follows:

  • Computer
  • Network
  • Server

You will also be responsible for planning and executing the project, with a focus on developing a risk management plan using the seven risk management processes, as follows:

  1. Planning
  2. Identification
  3. Qualitative risk assessment
  4. Quantitative risk assessment
  5. Response planning
  6. Response implementation
  7. Risk monitoring and control

Develop a communications managementplan that includes all project stakeholders andthe following elements:

  • Introduction narrative that explains the concepts of communications planning
  • The type of communication
  • Frequency of communication
  • Method of communication
  • Goals and objectives
  • Target audience
  • Who will distribute the communication?
  • Identify, construct, or provide an example of at least 3 risk status reports.Discuss the objectiveof the report and why it is needed.
  • Develop a change control process to address how change will be processed and approved or rejected.
  • Note: Tables or charts can be created for this assignment.

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Foodservice Management Principles And Practices

Authors: June Payne Palacio, Monica Theis

13th Edition

0133801101, 9780133801101

More Books

Students also viewed these General Management questions

Question

Answer clearly

Answered: 1 week ago

Question

The background knowledge of the interpreter

Answered: 1 week ago