Answered step by step
Verified Expert Solution
Link Copied!

Question

1 Approved Answer

Planned Costs and Financing for Golf Course The City plans to sell the bonds on February 1 , 2 0 2 1 . Because the

Planned Costs and Financing for Golf Course
The City plans to sell the bonds on February 1,2021. Because the bonds are a term
issue, bond principal matures in full on February 1,2031. Interest is payable each
August 1 and February 1, beginning August 1,2021. The bond covenant requires that
assets equal to one-tenth of the bond principal be transferred to a restricted account
within the GEF on December 31 of each year. Whitt observes a calendar fiscal year.
Simmons Design and Construction, Inc. (Simmons) has been awarded the contract
to develop the golf course. Construction will commence February 15,2021, and be
completed no later than May 31, so it can open for business during June. The
contract stipulates that progress billings from Simmons will be paid within 30 days
of receipt, with 5 percent retainage held pending completion and acceptance of the
project. The city engineer will inspect the contractor's work and approve progress
payments.
Accounting for the GEF will be done by the city's existing accounting department
(a General Fund department), which will bill the GEF for services rendered at the
end of the year. To help the GEF get on its feet financially, no interfund payables will
be settled in cash during 2021.
The following events and transactions occurred during the year ended December 31,2021:
January 3,2021: Whitt Falls formally established the GEF; the fund's first transaction
was the receipt, in cash, of the capital contribution from the General Fund.
January 24: The city acquired the adjacent parcel of land from the private owner
for the planned $500,000.
February 1: The revenue bonds were sold at par ( $3,000,000).
February 15: Development of the golf course itself and construction of the clubhouse
commenced.
March 31: Simmons submitted the first progress billing of $1,800,000. The billing was
approved and set up as a construction contracts payable after deducting the 5
percent retainage. (Because of the short duration of the construction period,
no construction in progress accounts will be used.) $400,000 of the amount billed
represents the cost of sod, sprinklers, landscaping, and fencing (which the city
classifies as "improvements other than buildings"). The balance applies to the cost
of the clubhouse ("buildings").
April 25: The construction contracts payable currently due Simmons was paid.April 30: The second progress billing from Simmons, $1,500,000, was approved and
set up as a construction contracts payable after deducting the 5 percent retainage;
$600,000 applies to sod, sprinklers, landscaping, and fencing (which is now fully
installed) with the remainder to the clubhouse building.
May 19: The construction contracts payable currently due Simmons was paid.
May 23: Simmons' third and final progress billing, $700,000(all of which represents
clubhouse construction costs), was approved and set up as a construction contracts
payable after deducting the 5 percent retainage.
May 30: The construction contracts payable currently due Simmons was paid.
June 1: The new golf course was formally accepted by the City (without need
for "touch-up" work), and all remaining amounts due to Simmons were paid.
June 1: The City acquired golf course maintenance equipment by entering into a 4-year
lease. The first lease payment of $50,000 was paid on June 2 when the equipment
was delivered. The remaining lease payments of $50,000 each will occur on the first,
second, and third anniversary of the first payment.
Assume that the interest rate on the lease is 4 percent.
June 2: Inventory in the amount of $12,000 was acquired for the pro shop; the
purchase created an accounts payable.
June 4: The course opened for business. Greens fees (charges for services)
aggregated $209,000 for June. Pro shop sales amounted to
$5,000. All revenues were collected.
June 30: Expenses for June were as follows. (Charge all expenses to "Operating
expenses-cost of sales.")
Maintenance and pro shop labor (paid in cash)- $48,000
Maintenance supplies, from the Parks DepartmentSpecial Revenue Fund - $4,000
(The invoice was received, but not paid.)
Water, supplied by the Whitt Falls water utility-an Enterprise Fund - $80,000
(The invoice was received, but not paid.)
Cost of merchandise sold by the pro shop - $2,200
August 1: The first debt service payment on the revenue bonds was made.
December 31: Greens fee revenues for the second half of 2021 totaled $370,000;
pro shop sales for the same period were
image text in transcribed

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Accounting Principles

Authors: Jerry J. Weygandt, Paul D. Kimmel, Donald E. Kieso, Weygandt Kimmel Kieso

10th Edition

0470646462, 978-0470646465

More Books

Students also viewed these Accounting questions

Question

Summarize various training methods.

Answered: 1 week ago

Question

Explain the metrics for evaluating training and development.

Answered: 1 week ago

Question

Identify career planning approaches.

Answered: 1 week ago