Please answer all 3 questions and explain. Thank you in advance ZZZ Corp. has a contract to construct a $5,000,000 cruise ship at an estimated

Please answer all 3 questions and explain. Thank you in advance

ZZZ Corp. has a contract to construct a $5,000,000 cruise ship at an estimated total cost of $4,000,000. The company will begin the construction in 2011 and expects to complete it in 2014. ZZZ Corp. has never constructed a cruise ship before and the customer has never operated a cruise ship, so there are inherent future risks in this construction. The company has the following activity in 2011:

Costs to date:$980,000

Estimated costs to complete:3,020,000

Progress billings during the year:1,000,000

Cash collected during the year:648,000

  1. Under IFRS, how much revenue should Swallow Corp. recognize on its 2011 income statement?
  2. Under IFRS, howmuch of construction in progress is reported on its 2011 balance sheet?
  3. Under IFRS, how much of accounts receivable is reported on its 2011 balance sheet?

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Accounting

Authors: Charles T Horngren, Walter T Harrison

9th Edition

132959674, 978-0132569057

More Books

Students also viewed these Accounting questions