Answered step by step
Verified Expert Solution
Link Copied!

Question

1 Approved Answer

Please answer all parts Schedule-Cost-Resource The table below contains cost, resource, and schedule data for a hypothetical project. Questions: Create a network diagram for the

Please answer all parts

  1. Schedule-Cost-Resource

The table below contains cost, resource, and schedule data for a hypothetical project.

image text in transcribed

Questions:

  1. Create a network diagram for the tasks listed in the table above.
  2. Calculate earliest start, latest start, and float for each task.

Task

Earliest start (ES)

Latest start (LS)

Float

A

B

C

D

E

F

  1. Given the information captured in the network diagram, create a Gantt chart for the project. In the Gantt chart, picture weekends. (Assume the project begins on a Tuesday and that a week of effort is five working days long.)
  2. Calculate level of effort, labor costs, and total costs per task and put the values in the appropriate cells in the first table above.
  3. Assume the company being examined here has only two testers. How will this show up on a resource histogram? How should the work for Tasks D and E be leveled? What, if any, impact will the resource leveling have on the project duration?
Total cost Immediate predecessor Duration (weeks) Number of resources Level of effort* Labor cost Material cost $1,000 $2,000 2 designers @$1,600 per week per person 2 programmers @$1,200 per week per person 1 programmer @$1,200 per week $2,000 $5,000 1 testers @ $1,000 per week per person 2 tester @ $1,000 per week per person $2,000 DE 3 $1,000 2 integrators @ $1,800 per week per person Total $13,000 * Level of effort = number of workers x duration of work; e.g., 5 people working 3 days is equal to 15 person-days of effort. Total cost Immediate predecessor Duration (weeks) Number of resources Level of effort* Labor cost Material cost $1,000 $2,000 2 designers @$1,600 per week per person 2 programmers @$1,200 per week per person 1 programmer @$1,200 per week $2,000 $5,000 1 testers @ $1,000 per week per person 2 tester @ $1,000 per week per person $2,000 DE 3 $1,000 2 integrators @ $1,800 per week per person Total $13,000 * Level of effort = number of workers x duration of work; e.g., 5 people working 3 days is equal to 15 person-days of effort

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Justified The Story Of Americas Audit

Authors: Dr. Kelli Ward

1st Edition

195725503X, 978-1957255033

More Books

Students also viewed these Accounting questions

Question

9. Describe the characteristics of power.

Answered: 1 week ago

Question

10. Describe the relationship between communication and power.

Answered: 1 week ago