Answered step by step
Verified Expert Solution
Link Copied!

Question

1 Approved Answer

Please answer b i), ii), iii) & c. Its all very short answer only a) Ahmad works as an Executive Planner in a construction company

Please answer b i), ii), iii) & c. Its all very short answer only

image text in transcribedimage text in transcribed

a) Ahmad works as an Executive Planner in a construction company in Kuantan. He identified all resources needed for a project. Explain TWO (2) aspects of work resource need to be consider by Ahmad when scheduling a project. [4 Marks] X Task Information General Predecessors Resources Advanced Notes Custom Fields Name: Scripting Duration: 2 wks Estimated Constrain task Deadline: NA Constraint type: As soon as possible Constraint date NA Task type: Fixed Units Effort driven Scheduling ignores resource calendars Calendar None WBS code 1.11 Earned value method: % Complete Mark task as milestone Help OK Cancel Figure 1 b) Figure 1 illustrates Task Information dialog box for Scripting task. Answer the following: i. Explain default for "Effort Driven. [2 Marks] ii. If the above project have two script writers, what will happen to the scripting task if two script writers were assigned? Explain why. [4 Marks] iii. Based on your answer in ii), what will happen if one of the script writer is unassigned from the task? Explain why. [4 Marks] Duration Predecessor 1 2 Task name Project X Task 1 25 days 10 days 3 Task 2 10 days 2FS+5 days 4 Task 3 5 days 3FS-5 days, 2FS+1 day Table 3 c) Based on the information in Table 3, draw possible Gantt chart. [6 Marks] a) Ahmad works as an Executive Planner in a construction company in Kuantan. He identified all resources needed for a project. Explain TWO (2) aspects of work resource need to be consider by Ahmad when scheduling a project. [4 Marks] X Task Information General Predecessors Resources Advanced Notes Custom Fields Name: Scripting Duration: 2 wks Estimated Constrain task Deadline: NA Constraint type: As soon as possible Constraint date NA Task type: Fixed Units Effort driven Scheduling ignores resource calendars Calendar None WBS code 1.11 Earned value method: % Complete Mark task as milestone Help OK Cancel Figure 1 b) Figure 1 illustrates Task Information dialog box for Scripting task. Answer the following: i. Explain default for "Effort Driven. [2 Marks] ii. If the above project have two script writers, what will happen to the scripting task if two script writers were assigned? Explain why. [4 Marks] iii. Based on your answer in ii), what will happen if one of the script writer is unassigned from the task? Explain why. [4 Marks] Duration Predecessor 1 2 Task name Project X Task 1 25 days 10 days 3 Task 2 10 days 2FS+5 days 4 Task 3 5 days 3FS-5 days, 2FS+1 day Table 3 c) Based on the information in Table 3, draw possible Gantt chart. [6 Marks]

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Bucks The Next Step Advanced Medical Coding And Auditing

Authors: Elsevier

1st Edition

0323874118, 978-0323874113

More Books

Students also viewed these Accounting questions