Question

1 Approved Answer

Please answer for all 9 parts for my second try, There is 2 pictures first picture shows the first try and all the questions going

Please answer for all 9 parts for my second try, There is 2 pictures first picture shows the first try and all the questions going to be asked (I got most of them wrong) . I want you to try solving all parts for the second try that has not wrong answers, it only shows part A. At the very least please do part A second try it will be the second picture.

image text in transcribedimage text in transcribed

a) The theoretical minimum number of workstations =5 (round your response up to the next whole number). b) The assignment of tasks to workstations should be: (Hint: Number workstations sequentially in terms of precedence relationships and combine any applicable tasks.) Were you able to assign all the activities to workstations equivalent to the theoretical minimum workstation? c) The efficiency of the assembly line =83.3% (enter your response as a percentage rounded to one decimal place). a) The theoretical minimum number of workstations = (round your response up to the next whole number)

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Applied Wildlife Habitat Management

Authors: Roel R. Lopez, Michael L. Morrison, Israel D. Parker

1st Edition

9781623495022

More Books

Students also viewed these General Management questions

Question

Determine miller indices of plane X z 2/3 90% a/3

Answered: 1 week ago