Question
Please answer part 1,2, and 3 please. Just to get the ball rolling, I am providing the step by step calculations for figure 13.1. Using
Please answer part 1,2, and 3 please.
Just to get the ball rolling, I am providing the step by step calculations for figure 13.1. Using my calculations as a guide, you need to show the step by step calculations, for parts I, II and III, for figure 13.2.
Part I: Project without the Growth Option:
NPV (Good): You can use row 2 of the calculator with the following inputs:
CF0 = -3000; C01 = 1500; F01 = 3; I = 12; CPT NPV; NPV = $603
Note: If you don't feel comfortable using the frequency key, you can enter the cash flows as follows:
CF0 = -3000; C01 = 1500; F01 = 1; C02 = 1500; F02 = 1; C03 = 1500; F03 =1
You follow the same procedure for the bad outcome and you get NPV = -$358
Expected NPV:
(.5*603) + (.5*(-358)) = $122
Standard Deviation:
SQRT[..5(603-122)^2 + .5(-358-122)^2] = $480
CV:
480/122 = 3.93
Part II: Project with the Option
The calculations are identical to part I. When you follow the calculations noted above, you get the following numbers:
Expected NPV = $1,503
Std. Dev. = $1,861
CV = 1.24
Part III: Value of the Option
Value of the option is the expected NPV with the option - expected NPV without the option. In this case:
Value of the option = $1,503 - $122 = $1,381
Notes:
1. If expected NPV without the option is negative, the project would not be accepted and so the option has no value.
2. Although the concepts in the four figures are fundamentally different, the calculations are identical.
Chapter 13 Real Options and Other Topics in Capital Budgeting 461 Part I. Project Without the Timing Option B FIGURE 13.3 Analysis of a Timing Option (dollars in thousands) A D G H 5 6 7 8 Prob 50% 50% NPV@ 12% $1,804 -$1,919 -$58 $1,861 -32.23 TO 11 13 16 77 18 19 20 Outcome Cash Flow at End of Period 0 Good 2 -$3,000 Bad $2.000 $2,000 $2,000 -$3,000 $450 $450 $450 Expected NPVI Standard Deviation (0) Coefficient of Variation - CVO / Expected NPV Part Il. Delry the Decision Until We Know the Market Conditions Dutcome Cash Flow at End of Period Prob. 0 1 2 Good 50% $0 -$3,000 $2,000 $2,000 Bad 50% SO $0 $0 $0 Expected NPV Standard Deviation (a) Coefficient of Variation = CV= / Expected NPVI 21 Part III. Value of the Option 22 Expected NPV with the timing option 23 Expected NPV without the timing option 24 25 CASE 1: If the expected NPV without the timing option is positive, then Expected NPV with the Expected NPV without Value of the Option = timing option the timing option NPV 12% $339 $0 $170 $170 1.00 $170 -$58 NA 27 28 CASE 2: If the expected NPV without the timing option is negative, then Value of the Option = Expected NPV with the 0 timing option $170 29 30 Note: If a negative NPV project does not have a timing option, then it would not be undertaken. In these cases, the expected NPV without the timing option is zero. 31 32 33 VALUE OF OPTION = $170 34 Note: Under the Delay situation, we must find the NPV as of t = 0. If we set the cash flow for t=0 at SO, then using a calculator or Excel, we automatically find the NPV at t = 0. However, if we let CF, =-3000, CF = 2000, N = 2, and I/YR = 12, we get an NPV = $380 under the Good outcome and an expected NPV of $190. Note, though, that these NPVs are as oft = 1, so we must discount them back year at 12% to achieve comparability with the NPV calculated for not delaying the project and arrive 35 at the correct answer. nditi will need and realize an NPV of $339,000, while and thus will have Chapter 13 Real Options and Other Topics in Capital Budgeting 461 Part I. Project Without the Timing Option B FIGURE 13.3 Analysis of a Timing Option (dollars in thousands) A D G H 5 6 7 8 Prob 50% 50% NPV@ 12% $1,804 -$1,919 -$58 $1,861 -32.23 TO 11 13 16 77 18 19 20 Outcome Cash Flow at End of Period 0 Good 2 -$3,000 Bad $2.000 $2,000 $2,000 -$3,000 $450 $450 $450 Expected NPVI Standard Deviation (0) Coefficient of Variation - CVO / Expected NPV Part Il. Delry the Decision Until We Know the Market Conditions Dutcome Cash Flow at End of Period Prob. 0 1 2 Good 50% $0 -$3,000 $2,000 $2,000 Bad 50% SO $0 $0 $0 Expected NPV Standard Deviation (a) Coefficient of Variation = CV= / Expected NPVI 21 Part III. Value of the Option 22 Expected NPV with the timing option 23 Expected NPV without the timing option 24 25 CASE 1: If the expected NPV without the timing option is positive, then Expected NPV with the Expected NPV without Value of the Option = timing option the timing option NPV 12% $339 $0 $170 $170 1.00 $170 -$58 NA 27 28 CASE 2: If the expected NPV without the timing option is negative, then Value of the Option = Expected NPV with the 0 timing option $170 29 30 Note: If a negative NPV project does not have a timing option, then it would not be undertaken. In these cases, the expected NPV without the timing option is zero. 31 32 33 VALUE OF OPTION = $170 34 Note: Under the Delay situation, we must find the NPV as of t = 0. If we set the cash flow for t=0 at SO, then using a calculator or Excel, we automatically find the NPV at t = 0. However, if we let CF, =-3000, CF = 2000, N = 2, and I/YR = 12, we get an NPV = $380 under the Good outcome and an expected NPV of $190. Note, though, that these NPVs are as oft = 1, so we must discount them back year at 12% to achieve comparability with the NPV calculated for not delaying the project and arrive 35 at the correct answer. nditi will need and realize an NPV of $339,000, while and thus will haveStep by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started