Please answer the following as true or false. 1. Retainage does not impact the project level cash flow, because most of the retainer is just

Please answer the following as true or false.

1. Retainage does not impact the project level cash flow, because most of the retainer is just profits.

2.Though common with GMP, or lump-sum contracts, retainage is not as common for costs-plus contracts.

3. The schedule of values is a communication tool between the contractor and the owner, and generally becomes part of the contract.

Group of answer choices

4. The schedule of values can be used by the owner to establish pricing for additive and deductive change orders.

5. The schedule of values is essentially a summary of construction activities and the dollar value of those activities.

6. The contractor does not always include their fee, markup, or general conditions in the schedule of values. Instead, they may choose to pro-rate those items and embed them into other construction activities.

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Corporate Finance Principles And Practice

Authors: Denzil Watson, Tony Head

1st Edition

0273630083, 978-0273630081

More Books

Students also viewed these Finance questions