Answered step by step
Verified Expert Solution
Question
1 Approved Answer
Please answer the following question with the complete steps: EVM Exercise: The Fence #2 You have a project to build a new fence. The fence
Please answer the following question with the complete steps:
EVM Exercise: The Fence #2 You have a project to build a new fence. The fence is four sided as shown. Each side is to take one day to build and is budgeted for $1,000 per side. The sides are planned to be completed one after the other. IN THIS CASE ASSUME THAT THE SIDES HAVE A FINISH-TO-FINISH RELATIONSHIP INSTEAD OF A FINISH- TO-START RELATIONSHIP. Today is the end of the third day. Using the project status chart below, calculate EV, etc. Interpretation is also important. Can you interpret what each answer means? Task Day 1 Day 2 Day 3 Day 4 Status at the End of Day 3 Side 1 S---- --F Complete; spent $1,000 Side 2 S---F---PF Complete; spent $900 Side 3 S - - -- PS---. -PF 50% done; spent $1000 Side 4 PS--------PF 75% done; spent $300 KEY: S = Actual Start F = Actual Finish PS = Planned Start PF = Planned Finish What is : Calculation Answer Interpretation of the Answer PV EV AC BAC CV CPI SV SPI EAC ETC VAC
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started