Please answer the following question with the complete steps: EVM Exercise: The Fence #2 You have a project to build a new fence. The fence

Please answer the following question with the complete steps:

image text in transcribed
EVM Exercise: The Fence #2 You have a project to build a new fence. The fence is four sided as shown. Each side is to take one day to build and is budgeted for $1,000 per side. The sides are planned to be completed one after the other. IN THIS CASE ASSUME THAT THE SIDES HAVE A FINISH-TO-FINISH RELATIONSHIP INSTEAD OF A FINISH- TO-START RELATIONSHIP. Today is the end of the third day. Using the project status chart below, calculate EV, etc. Interpretation is also important. Can you interpret what each answer means? Task Day 1 Day 2 Day 3 Day 4 Status at the End of Day 3 Side 1 S---- --F Complete; spent $1,000 Side 2 S---F---PF Complete; spent $900 Side 3 S - - -- PS---. -PF 50% done; spent $1000 Side 4 PS--------PF 75% done; spent $300 KEY: S = Actual Start F = Actual Finish PS = Planned Start PF = Planned Finish What is : Calculation Answer Interpretation of the Answer PV EV AC BAC CV CPI SV SPI EAC ETC VAC

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Human Resources Management In The Hospitality Industry

Authors: David K Hayes, Jack D Ninemeier

1st Edition

0470084804, 9780470084809

More Books

Students also viewed these General Management questions