Please answer the following. Reference: Linear Programming 3. MP Construction Company wants to determine the least number of daily workers for the construction of a

Please answer the following. Reference: Linear Programming

image text in transcribedimage text in transcribed
3. MP Construction Company wants to determine the least number of daily workers for the construction of a new 500-acre high-class subdivision at San Pedro, Laguna. Only two types of skilled workers are considered for this phase of the construction. Welders are paid 1000 PhP per day while Electrical Technicians are paid 1500 per day. The company conducted various studies and consulted several experts for the worker allocations for this project phase. According to a scheduling study, the number of Welders should be at least 6% of the number of Electrical Technicians. Also, according to a time study, 20 times of the number of Welders should be at work with at most 7 times of the number of Electrical Technicians. Both of these studies must be considered. The Engineer in charge recommended that 9 times of the number of Welders should be present with at most twice the number of Electrical Technicians. On theother hand, the Architects recommended that there should be at least 90 Welders and at least 800 Electrical Technicians. For safety and quality requirements, the total number of workers must be at least 1000. The company is having a problem determining the least cost while considering all these studies, recommendations, and requirements. As an expert in quantitative methods, they hired you to help them solve their dilemma. What would you say to the board of directors as a solution to their problem? They also asked you the least total cost for the whole project phase considering that the project phase would run for 7 months (25 working days per month). Scoring Guide: Requirements Points Decision variables 5 Objective Function 5 Constraints 10 Graph 15 Graphical Solution 10 Analytical Solution 10 Solution using POM-QM Software (Table 15 and graph) Explanation to the board of directors 10 Least total cost for 7 months 10 Total Points 90 Requirements: Show the organized complete and full detailed solution for each item. Tip: You can check your work using Desmos or the POM-QM Software

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Finite Mathematics

Authors: Margaret L. Lial, Raymond N. Greenwell, Nathan P. Ritchey

10th Edition

0321748999, 9780321748997

More Books

Students also viewed these Mathematics questions