please as soon as possible The process design team at a manufacturer has broken an assembly process into eight basic tasks, each with a required
please as soon as possible The process design team at a manufacturer has broken an assembly process into eight basic tasks, each with a required time and predecessor as shown in the table. They work 7 hours a day and want to produce at a rate of 360 units per day. Task: Time (sec) Predecessor A 40 B 35 A 30 D 40 , E 25 D F 50 D G 20 H 30 F,G Total: 270 (sec) What is the required cycle time