Please explain in detail your answer! The following data are average times per order over the last month. Wait time to start production 16.2 days
Please explain in detail your answer!
The following data are average times per order over the last month.
Wait time to start production 16.2 days
Inspection time 1.8 days
Process time 2.7 days
Move time 2.6 days
Queue time 8.2 days
The manufacturing cycle efficiency (MCE) would be closest to:
A. 29%.
B. 82%.
C. 46%.
D. 18%.
E. None of the above