Question
Please Help - Change Management Plan This section should describe your change control process. Ideally, this process will be some type of organizational standard which
Please Help -
Change Management Plan
This section should describe your change control process. Ideally, this process will be some type of organizational standard which is repeatable and done on most or all projects when a change is necessary. Changes to any project must be carefully considered and the impact of the change must be clear in order to make any type of approval decisions. Many organizations have change control boards (CCBs) which review proposed changes and either approve or deny them. This is an effective way to provide oversight and ensure adequate feedback and review of the change is obtained. This section should also identify who has approval authority for changes to the project, who submits the changes, how they are tracked and monitored.
For complex or large projects the Change Management Plan may be included as an appendix to the Project Management Plan or as a separate, stand-alone document. We have a detailed Change Management Plan template available on our website.
The following steps comprise TSI's organization change control process for all projects and will be utilized on the SmartVoice project:
Step #1:
Step #1: Identify the need for a change (Any Stakeholder)
Requestor will submit a completed TSI change request form to the project manager
Step #2: Log change in the change request register (Project Manager)
The project manager will maintain a log of all change requests for the duration of the project
Step #3: Conduct an evaluation of the change (Project Manager, Project Team, Requestor) The project manager will conduct an evaluation of the impact of the change to cost, risk, schedule, and scope
Step #4: Submit change request to Change Control Board (CCB) (Project Manager)
The project manager will submit the change request and analysis to the CCB for review
Step #5: Change Control Board decision (CCB)
The CCB will discuss the proposed change and decide whether or not it will be approved based on all submitted information
Step #6: Implement change (Project Manager)
If a change is approved by the CCB, the project manager will update and re-baseline project documentation as necessary as well as ensure any changes are communicated to the team and stakeholders
Any team member or stakeholder may submit a change request for the SmartVoice Project. The SmartVoice Project Sponsor will chair the CCB and any changes to project scope, cost, or schedule must meet his approval. All change requests will be logged in the change control register by the Project Manager and tracked through to completion whether approved or not.
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started