Budget Allocations
ID | Budget ($000) | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 | 11 | 12 |
A | 40 | 10 | 10 | 10 | 10 | ||||||||
B | 32 | 8 | 4 | 8 | 4 | 8 | |||||||
C | 48 | 12 | 12 | 12 | 12 | ||||||||
D | 18 | 6 | 2 | 2 | 2 | 6 | |||||||
E | 28 | 8 | 8 | 12 | |||||||||
F | 40 | 20 | 20 | ||||||||||
Total | 206 | 18 | 14 | 18 | 14 | 20 | 26 | 22 | 26 | 2 | 6 | 20 | 20 |
Cumulative | 18 | 32 | 50 | 64 | 84 | 110 | 132 | 158 | 160 | 166 | 186 | 206 |
Status Reports
Status Report: Ending Period 2 | ($000) | |||||
Task | % Complete | EV | AC | PV | CV | SV |
A | 75% | ----- | 25 | ----- | ----- | ----- |
B | 50% | ----- | 12 | ----- | ----- | ----- |
Cumulative Totals | ----- | 37 | ----- | ----- | ----- | |
Status Report: Ending Period 4 | ($000) | |||||
Task | % Complete | EV | AC | PV | CV | SV |
A | 100% | ----- | 35 | ----- | ----- | ----- |
B | 100% | ----- | 24 | ----- | ----- | ----- |
Cumulative Totals | ----- | 59 | ----- | ----- | ----- | |
Status Report: Ending Period 6 | ($000) | |||||
Task | % Complete | EV | AC | PV | CV | SV |
A | 100% | ----- | 35 | ----- | ----- | ----- |
B | 100% | ----- | 24 | ----- | ----- | ----- |
C | 75% | ----- | 24 | ----- | ----- | ----- |
D | 0% | ----- | 0 | ----- | ----- | ----- |
E | 50% | ----- | 10 | ----- | ----- | ----- |
Cumulative Totals | ----- | 93 | ----- | ----- | ----- | |
Status Report: Ending Period 8 | ($000) | |||||
Task | % Complete | EV | AC | PV | CV | SV |
A | 100% | ----- | 35 | ----- | ----- | ----- |
B | 100% | ----- | 24 | ----- | ----- | ----- |
C | 100% | ----- | 32 | ----- | ----- | ----- |
D | 33% | ----- | 20 | ----- | ----- | ----- |
E | 100% | ----- | 20 | ----- | ----- | ----- |
Cumulative Totals | ----- | 131 | ----- | ----- | ----- | |
Performance Indexes Summary | ||||||
Period | EV | AC | PV | SPI | CPI | PCIB |
2 | ----- | ----- | ----- | ----- | ----- | ----- |
4 | ----- | ----- | ----- | ----- | ----- | ----- |
6 | ----- | ----- | ----- | ----- | ----- | ----- |
8 | ----- | ----- | ----- | ----- | ----- | ----- |
EAC = _____________ | VAC = _____________ |
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started