Please help find the discounted payback period for the project.The discount rate is 10% Initial outlay is $16853 Year 1 $5625 Year 2 $5504 Year
Please help find the discounted payback period for the project.The discount rate is 10%
Initial outlay is $16853
Year 1 $5625
Year 2 $5504
Year 3 $5892
Year 4 $8851