Question

1 Approved Answer

please help me on these! The order cycle time of Bake LCC is 12 days to complete and the buyer needs 25 units per day

please help me on these! image text in transcribed
image text in transcribed
image text in transcribed
The order cycle time of Bake LCC is 12 days to complete and the buyer needs 25 units per day for its manufacturing process. Assuming the basic economic order quantity (EOQ) is being used by the buyer, the buyer will place an order when it has _ units of demand inventory on hand. Provide your calculations. Assuming that Bake LCC has been able to reduce the order cycle to 8 day. the buyer will now place an order when it has units of demand inventory hand. And the reduction of units of demand in inventory. Provide your calculations. Now assume that Bake LLC has a 12-day order cycle time has a variability of +14 days, producing a range of for the order cycle. If the buyer wants to ensure that no stockouts occur for its manufacturing process, it must place an order when it has units of inventory on hand

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image_2

Step: 3

blur-text-image_3

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

ISE Entrepreneurship

Authors: Robert Hisrich, Michael Peters, Dean Shepherd

11th International Edition

1260565629, 1260565621, 1260564068, 1260564061, 9781260043730, 1260043738, 978-1260565621

More Books

Students also viewed these General Management questions