Question
Please help with this: You are a builder of high-end custom garages, and you advertise that your firm builds quality garages quickly and cheaply. You
Please help with this: You are a builder of high-end custom garages, and you advertise that your firm builds quality garages quickly and cheaply. You often do work for builders, and you are about to share your status report with your customer.
How much should have been spent by 10/12?
What is the Earned Value as of 10/12?
What is the Schedule Variance as of 10/12?
What is the Schedule Performance Index and Cost Performance index as of 10/12? (you can express as a fraction or the actual number.) One point for each, and indicate which number is which answer!
A- What information would you share with the customer?
B- Would you forecast being late with the final delivery? Early? Over budget?
You are a builder of high end custom garages, and you advertise that your firm builds quality grarages quick and cheap You often do work for builders, and you are about to share your status report with your customer. Please analyze the following data from your project team Task Name Duration Star Finish Predecessors Cost Actual Start Actual Finish Actual Cost %complete Kickoff - selected as 1 day? Mon 9/10/18 Mon 9/10/18 $0.00 Mon 9/10/18 Mon 9/10/18 $0.00 100 Negotiate contract 2 days Tue 9/11/18 Wed 9/12/18 $200.00 Tue 9/11/18 9/13 $180.00 100 Send finalized spec 2 days Thu 9/13/18 Fri 9/14/18 $200.00 9/14 9/14 $220.00 100 Specification appro 2 days Mon 9/17/18 Tue 9/18/18 $200.00 9/17 9/2 $250.00 100 Obtain customer si 5 days Wed 9/19/18 Tue 9/25/18 $400.00 /23 0/1 $750.00 100 Buy materials 2 days Wed 9/26/18 Thu 9/27/18 LO CO V ON UI A W N H $1,500.00 10/1 10/3 $1,250.00 100 Pour foundation 2 days Fri 9/28/18 Mon 10/1/18 $1,000.00 10/3 10/5 $1,250.00 100 Build wall 2 days Tue 10/2/18 Wed 10/3/18 $500.00 10/5 10/8 $400.00 100 Install roof 2 days Thu 10/4/18 Fri 10/5/18 $500.00 10/7 10/9 $600.00 00 Install doors 5 days Mon 10/8/18 Fri 10/12/18 $500.00 10/9 NA $750.00 30 Paint exterior 4 days Mon 10/15/18 Thu 10/18/18 10 $1,000.00 NA NA $0.00 Finish interior 3 days Fri 10/19/18 Tue 10/23/18 11 $1,000.00 NA NA $0.00 Final acceptance te 1 day Wed 10/24/18 Thu 10/25/18 12 $500.00 NA NA $0.00 0 Resolve defects 13 days Fri 10/26/18 Tue 10/30/18 13 $300.00 NA NA $0.00 0 Obtain customer si 0 days Wed 10/31/18 Wed 10/31/18 14 $200.00 NA NA $0.00 0 Close out the order 1 day? Thu 11/1/18 Thu 11/1/18 $0.00 NA NA $0.00 $8,000.00 $5,650.00Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started