Please, I want a solution, I did not understand the question Car factory planned to use $72 of material per unit but actually used $70
Please, I want a solution, I did not understand the question
Car factory planned to use $72 of material per unit but actually used $70 of material per unit. and planned to make 1.200 units but actually made 1.000 units The sales-volume variance is:
Step by Step Solution
There are 3 Steps involved in it
Step: 1