Question
Please note: different from previous questions, this question is using chase strategy. Osprey Machine Works has the following demand requirements and other data for the
Please note: different from previous questions, this question is using chase strategy.
Osprey Machine Works has the following demand requirements and other data for the upcoming four quarters. What is the associated cost in quarter 1 if chase strategy adopted?
Quarter | Demand | Previous quarter's output | 2500 units |
1 | 2300 | Beginning inventory | 200 units |
2 | 2400 | Stockout (backorder) cost | $50 per unit |
3 | 2600 | Inventory holding cost | $10 per unit at end of quarter |
4 | 2100 | Hiring workers | $4 per unit |
Laying off workers | $8 per unit |
Question 10 options:
$2500 | |
$2000 | |
$3200 | |
$1600 |
Hide hint for Question 10 | |
please note: (1) the initial inventory 200 will be used to partly meet the demand of quarter 1. (2) find out the production change of quarter 1 based on previous quarter's level 2500 |
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started