Vance Asbestos Removal Company removes potentially toxic asbestos insulation and related products from buildings. The companys estimator has been involved in a long-simmering dispute with the on-site work supervisors. The on-site supervisors claim that the estimator does not adequately distinguish between routine work, such as removal of asbestos insulation around heating pipes in older homes, and non-routine work, such as removing asbestos-contaminated ceiling plaster in industrial buildings. The on-site supervisors believe that non-routine work is far more expensive than routine work and should bear higher customer charges. The estimator sums up his position in this way: My job is to measure the area to be cleared of asbestos. As directed by top management, I simply multiply the square metres by $4,900 per thousand square metres to determine the bid price. Since our average cost is only $3,900 per thousand square metres, that leaves enough cushion to take care of the additional costs of non-routine work that shows up. Besides, it is difficult to know what is routine or not routine until you actually start tearing things apart.

To shed light on this controversy, the company initiated an ABC study of all of its costs. Data from the ABC system follow:

Activity Cost Pool Activity Measure Total Activity
Removing asbestos Thousands of square metres 500,000 m2
Estimating and job setup Number of jobs 250 jobs*
Working on non-routine jobs Number of non-routine jobs 27 non-routine jobs
Other (costs of idle capacity and organization-sustaining costs) Not applicable; these costs are not allocated to jobs.

* The total number of jobs includes non-routine jobs as well as routine jobs. Non-routine jobs as well as routine jobs require estimating and setup work.

Wages and salaries $ 290,000
Disposal fees 735,000
Equipment depreciation 107,000
On-site supplies 78,000
Office expenses 262,000
Licensing and insurance 478,000
Total cost $ 1,950,000

Distribution of Resource Consumption across Activity Cost Pools:

Removing Asbestos Estimating and Job Setup Working on Non-routine Jobs Other Total
Wages and salaries 40% 10% 35% 15% 100%
Disposal fees 75% 0% 25% 0% 100%
Equipment depreciation 45% 0% 40% 15% 100%
On-site supplies 50% 15% 25% 10% 100%
Office expenses 10% 40% 30% 20% 100%
Licensing and insurance 50% 0% 45% 5% 100%
image text in transcribed Required: 1. Perform the first-stage allocation of costs to the activity cost pools. (Do not leave any empty spaces; input a 0 wherever it is required.) 2. Compute the activity rates for the activity cost pools. (Round your answers to 2 decimal places.)

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access with AI-Powered Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Students also viewed these Accounting questions