Please provide MS Project and Gantt screenshot also the results! Thanks Critical Chain You are a project manager, and about to develop a schedule for

Please provide MS Project and Gantt screenshot also the results! Thanks

Critical Chain

You are a project manager, and about to develop a schedule for a new project consisting of tasks A through G below. Please assume that the durations in this table are based on traditional estimates, and that Task A without starts on August 14th of this year (as shown). Also, please assume a regular 5-day work week without special arrangements for the holidays (i.e., we are not taking time off for Labor Day!)

image text in transcribed
Task Name Duration Start Predecessors A 4 days Mon 8/14/23 B 8 days A C 20 days A D 4 days B E 4 days C F 12 days C,D G 8 days E,F

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access with AI-Powered Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Business Communication

Authors: Peter Cardon

4th Edition

1264109075, 9781264109074

More Books

Students also viewed these General Management questions