Answered step by step
Verified Expert Solution
Link Copied!

Question

1 Approved Answer

Please see the attached document. Introduction All of you have had at least an introduction to earned value management in the project management fundamentals course.

image text in transcribed

Please see the attached document.

Introduction

All of you have had at least an introduction to earned value management in the project management fundamentals course. Many of you may have had the opportunity to use earned value management in your professional careers. In practice, most EVM analysis results are generated by scheduling software or other applications. As a project manager, you must have a good handle on the concepts and be able to verify the accuracy of EVM analysis results.

In this assignment, you will have an opportunity to brush up and expand upon your EVM knowledge and skills by applying EVM concepts to a practical problem. THIS ASSIGNMENT REQUIRES A MANUAL ANALYSIS - DO NOT USE MICROSOFT PROJECT.

Problem Background

Your project consists of seven activities shown in the table below, along with: (1) planned start and finish dates; (2) activity budgets; and (3) earned value (EV) accrual rules from you project cost management plan.

Assumptions

  • Assume a five-day work week including holidays occurring during the work week.
  • For all activities (except activities 3 and 4), assume the expenditure rate is constant over the duration of the activity, i.e., the amount planned to be spent each week is the same.
  • For activity 3, the planned expenditure profile is shown below:
  • For activity 4, the planned expenditure profile is shown below:

The project sponsor wants you (the PM) to present a project cost and schedule performance assessment using data through Friday, July 29, 2016. You have collected the following information:

For activity 1, three equally-valued gates have been established and all gates are complete as of July 29, 2016.

For activity 3, five milestones have been established with the following values: (1) milestone 1 - 10%; milestone - 20%; milestone 3 - 15%; milestone 4 -20%; milestone 5 - 35%. Four of the milestones are complete as of July 29, 2016.

For activity 4, four equally values gates have been established. As of July 29, 2016 none of the gates have been reached but the activity owner estimates 30% of the work required to reach the first gate has been accomplished.

Show all work. Round dollar values to the nearest dollar. Calculate all other variables to three decimal places.

Earned Value MeasuresCalculate earned value measures for each activity and for the cumulative project as of July 29, 2016; fill in the table below:Earned Value Performance MeasuresCalculate earned value performance parameters for each activity and for the cumulative project as of July 29, 2016; fill in the table below:

Activity

  • Is the project ahead of schedule, on schedule, or behind schedule? What EVM information are you using to make this assessment and why?
  • Is the project over budget, under budget, or on budget? What EVM information are you using to make this assessment and why?
  • Earned Value Forecasts
  • What is the value of the "Cumulative CPI" Estimate-at-Completion (EAC)?
  • Using the "Mathematical" or "Overrun to Date" Estimate-at Completion, what is the value of the Estimate-to-Complete (ETC)?
  • Using the "Cumulative CPI times SPI" Estimate-At-Completion, how much more or less money (other than the current budgeted amount) will you need to finish the project?
  • How much would the Cost Performance Index (CPI) have to change in order to complete the project within the original budget?Introduction

    All of you have had at least an introduction to earned valuemanagement in the project management fundamentals course. Many of you may havehad the opportunity to use earned value management in your professionalcareers. In practice, most EVM analysis results are generated by schedulingsoftware or other applications. As a project manager, you must have a goodhandle on the concepts and be able to verify the accuracy of EVM analysisresults.

    In this assignment,you will have an opportunity to brush up and expand upon your EVM knowledge andskills by applying EVM concepts to a practical problem. THIS ASSIGNMENTREQUIRES A MANUAL ANALYSIS - DO NOT USE MICROSOFT PROJECT.

    Problem Background

    Your project consists of seven activities shown in the tablebelow, along with: (1) planned start and finish dates; (2) activity budgets;and (3) earned value (EV) accrual rules from you project cost management plan.

    Assumptions

    1.Assume a five-day work week including holidaysoccurring during the work week.

    2.For all activities (except activities 3 and 4), assumethe expenditure rate is constant over the duration of the activity, i.e., theamount planned to be spent each week is the same.

    3.For activity 3, the planned expenditure profileis shown below:

    4.For activity 4, the planned expenditure profileis shown below:

    The project sponsor wants you (the PM) to present a projectcost and schedule performance assessment using data through Friday, July 29,2016. You have collected the following information:

    For activity 1, three equally-valued gates have beenestablished and all gates are complete as of July 29, 2016.

    For activity 3, five milestones have been established withthe following values: (1) milestone 1 - 10%; milestone - 20%; milestone 3 - 15%;milestone 4 -20%; milestone 5 - 35%. Four of the milestones are complete as of July29, 2016.

    For activity 4, four equally values gates have beenestablished. As of July 29, 2016 none of the gates have been reached but theactivity owner estimates 30% of the work required to reach the first gate hasbeen accomplished.

    Show allwork. Round dollar values to the nearest dollar. Calculate all other variablesto three decimal places.

    1.Earned Value Measures

    a.Calculate earned value measures for eachactivity and for the cumulative project as of July 29, 2016; fill in the tablebelow:

    Activity

    Planned Value (PV)

    Earned Value (EV)

    Actual Cost (AC)

    Activity One

    22,000

    Activity Two

    25,000

    Activity Three

    40,000

    Activity Four

    8,000

    Activity Five

    0

    Activity Six

    0

    Activity Seven

    0

    Entire Project

    2.Earned Value Performance Measures

    a.Calculate earned value performance parametersfor each activity and for the cumulative project as of July 29, 2016; fill inthe table below:

    Activity

    Schedule Variance (SV)

    Schedule Performance Index (SPI)

    Cost Variance (CV)

    Cost Performance Index (CPI)

    Activity One

    Activity Two

    Activity Three

    Activity Four

    Activity Five

    Activity Six

    Activity Seven

    Entire Project

    b.Is the project ahead of schedule, on schedule,or behind schedule? What EVM information are you using to make this assessmentand why?

    c.Is the project over budget, under budget, or onbudget? What EVM information are you using to make this assessment and why?

    3.Earned Value Forecasts

    a.What is the value of the "Cumulative CPI" Estimate-at-Completion(EAC)?

    b.Using the "Mathematical" or "Overrun to Date"Estimate-at Completion, what is the value of the Estimate-to-Complete (ETC)?

    c.Using the "Cumulative CPI times SPI"Estimate-At-Completion, how much more or less money (other than the currentbudgeted amount) will you need to finish the project?

    d.How much would the Cost Performance Index (CPI)have to change in order to complete the project within the original budget?

image text in transcribed PMAN 650 Session 5 Individual Assignment (v3) Earned Value Management Introduction All of you have had at least an introduction to earned value management in the project management fundamentals course. Many of you may have had the opportunity to use earned value management in your professional careers. In practice, most EVM analysis results are generated by scheduling software or other applications. As a project manager, you must have a good handle on the concepts and be able to verify the accuracy of EVM analysis results. In this assignment, you will have an opportunity to brush up and expand upon your EVM knowledge and skills by applying EVM concepts to a practical problem. THIS ASSIGNMENT REQUIRES A MANUAL ANALYSIS - DO NOT USE MICROSOFT PROJECT. Problem Background Your project consists of seven activities shown in the table below, along with: (1) planned start and finish dates; (2) activity budgets; and (3) earned value (EV) accrual rules from you project cost management plan. Assumptions 1. Assume a five-day work week including holidays occurring during the work week. 2. For all activities (except activities 3 and 4), assume the expenditure rate is constant over the duration of the activity, i.e., the amount planned to be spent each week is the same. 3. For activity 3, the planned expenditure profile is shown below: PMAN 650 Session 5 Individual Assignment (v3) Earned Value Management 4. For activity 4, the planned expenditure profile is shown below: The project sponsor wants you (the PM) to present a project cost and schedule performance assessment using data through Friday, July 29, 2016. You have collected the following information: PMAN 650 Session 5 Individual Assignment (v3) Earned Value Management For activity 1, three equally-valued gates have been established and all gates are complete as of July 29, 2016. For activity 3, five milestones have been established with the following values: (1) milestone 1 - 10%; milestone - 20%; milestone 3 - 15%; milestone 4 -20%; milestone 5 - 35%. Four of the milestones are complete as of July 29, 2016. For activity 4, four equally values gates have been established. As of July 29, 2016 none of the gates have been reached but the activity owner estimates 30% of the work required to reach the first gate has been accomplished. Show all work. Round dollar values to the nearest dollar. Calculate all other variables to three decimal places. 1. Earned Value Measures a. Calculate earned value measures for each activity and for the cumulative project as of July 29, 2016; fill in the table below: Activity Activity One Activity Two Activity Three Activity Four Activity Five Activity Six Activity Seven Entire Project Planned Value (PV) Earned Value (EV) Actual Cost (AC) 22,000 25,000 40,000 8,000 0 0 0 2. Earned Value Performance Measures a. Calculate earned value performance parameters for each activity and for the cumulative project as of July 29, 2016; fill in the table below: Activity Activity One Activity Two Activity Three Activity Four Schedule Variance (SV) Schedule Performance Index (SPI) Cost Variance (CV) Cost Performance Index (CPI) PMAN 650 Session 5 Individual Assignment (v3) Earned Value Management Activity Five Activity Six Activity Seven Entire Project b. Is the project ahead of schedule, on schedule, or behind schedule? What EVM information are you using to make this assessment and why? c. Is the project over budget, under budget, or on budget? What EVM information are you using to make this assessment and why? 3. Earned Value Forecasts a. What is the value of the \"Cumulative CPI\" Estimate-at-Completion (EAC)? b. Using the \"Mathematical\" or \"Overrun to Date\" Estimate-at Completion, what is the value of the Estimate-to-Complete (ETC)? c. Using the \"Cumulative CPI times SPI\" Estimate-At-Completion, how much more or less money (other than the current budgeted amount) will you need to finish the project? d. How much would the Cost Performance Index (CPI) have to change in order to complete the project within the original budget

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Management Science The Art Of Modeling With Spreadsheets

Authors: Stephen G. Powell, Kenneth R. Baker

3rd Edition

0470530677, 978-0470530672

More Books

Students also viewed these Finance questions

Question

What are the short- and long-term effects of stress on the body?

Answered: 1 week ago