PLEASE SHOW CALCULATOR INPUTS A project has been assigned a discount rate of 12 percent. If the project starts immediately, it will have an initial
PLEASE SHOW CALCULATOR INPUTS
A project has been assigned a discount rate of 12 percent. If the project starts immediately, it will have an initial cost of $480 and cash inflows of $350 a year for three years. If the start is delayed one year, the initial cost will rise to $520 and the cash flows will increase to $385 a year for three years. What is the value of the option to wait?