PLEASE SHOW ME THE WORK FOR THE FOLLOWING QUESTION: The following data for a pottery company pertain to the production of 2,000 clay pots during
PLEASE SHOW ME THE WORK FOR THE FOLLOWING QUESTION:
The following data for a pottery company pertain to the production of 2,000 clay pots during July.
Direct Materials (all materials purchased were used):
Standard cost: $2.00 per kilogram of clay
Total actual cost: $10,640
Standard cost allowed for units produced was $12,000
Materials quantity variance was $800 favourable
Direct Manufacturing Labour:
Standard cost is 2 pots per hour at $24.00 per hour
Actual cost per hour was $24.50
Actual labour was 1028 hours
What is thelabour efficiencyvariance?
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started