please show work on how to calculate all parts. Consider a project to supply Detroit with 20,000 tons of machine screws annually for automobile production.

image text in transcribed

image text in transcribed

please show work on how to calculate all parts.

Consider a project to supply Detroit with 20,000 tons of machine screws annually for automobile production. You will need an initial $3,000,000 investment in threading equipment to get the project started; the project will last for four years. The accounting department estimates that annual fixed costs will be $850,000 and that variable costs should be $450 per ton; accounting will depreciate the initial fixed asset investment straight-line to zero over the four-year project life. It also estimates a salvage value of $280,000 after dismantling costs. The marketing department estimates that the automakers will let the contract at a selling price of $600 per ton. The engineering department estimates you will need an initial net working capital investment of $300,000. You require a return of 18 percent and face a marginal tax rate of 38 percent on this project ok at nces Suppose you're confident about your own projections, but you're a little unsure about Detroit's actual machine screw requirement. a. What is the sensitivity of the project OCF to changes in the quantity supplied? (Do not round intermediate calculations and round your final answer to 2 decimal places (e.g., 32.16).) AOCFIAQ b. What is the sensitivity of NPV to changes in quantity supplied? (Do not round intermediate calculations and round your final answer to 2 decimal places (e.g., 32.16).) ANPVIAQ $ Prev 2 of 5 Next > cung uepartment estimates that the automakers will let the contract at a selling price of $600 per ton. The engineering department estimates you will need an initial net working capital investment of $300,000. You require a return of 18 percent and face a marginal tax rate of 38 percent on this project Suppose you're confident about your own projections, but you're a little unsure about Detroit's actual machine screw requirement. a. What is the sensitivity of the project OCF to changes in the quantity supplied? (Do not round intermediate calculations and round your final answer to 2 decimal places (e.g., 32.16).) es AOCFAQ b. What is the sensitivity of NPV to changes in quantity supplied? (Do not round intermediate calculations and round your final answer to 2 decimal places (e.g., 32.16).) ANPVIAC c. Given the sensitivity number you calculated, is there some minimum level of output below which you wouldn't want to operate? (Do not round intermediate calculations and round your final answer to the nearest whole number.) Minimum level of output units ere to search Consider a project to supply Detroit with 20,000 tons of machine screws annually for automobile production. You will need an initial $3,000,000 investment in threading equipment to get the project started; the project will last for four years. The accounting department estimates that annual fixed costs will be $850,000 and that variable costs should be $450 per ton; accounting will depreciate the initial fixed asset investment straight-line to zero over the four-year project life. It also estimates a salvage value of $280,000 after dismantling costs. The marketing department estimates that the automakers will let the contract at a selling price of $600 per ton. The engineering department estimates you will need an initial net working capital investment of $300,000. You require a return of 18 percent and face a marginal tax rate of 38 percent on this project ok at nces Suppose you're confident about your own projections, but you're a little unsure about Detroit's actual machine screw requirement. a. What is the sensitivity of the project OCF to changes in the quantity supplied? (Do not round intermediate calculations and round your final answer to 2 decimal places (e.g., 32.16).) AOCFIAQ b. What is the sensitivity of NPV to changes in quantity supplied? (Do not round intermediate calculations and round your final answer to 2 decimal places (e.g., 32.16).) ANPVIAQ $ Prev 2 of 5 Next > cung uepartment estimates that the automakers will let the contract at a selling price of $600 per ton. The engineering department estimates you will need an initial net working capital investment of $300,000. You require a return of 18 percent and face a marginal tax rate of 38 percent on this project Suppose you're confident about your own projections, but you're a little unsure about Detroit's actual machine screw requirement. a. What is the sensitivity of the project OCF to changes in the quantity supplied? (Do not round intermediate calculations and round your final answer to 2 decimal places (e.g., 32.16).) es AOCFAQ b. What is the sensitivity of NPV to changes in quantity supplied? (Do not round intermediate calculations and round your final answer to 2 decimal places (e.g., 32.16).) ANPVIAC c. Given the sensitivity number you calculated, is there some minimum level of output below which you wouldn't want to operate? (Do not round intermediate calculations and round your final answer to the nearest whole number.) Minimum level of output units ere to search

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Commodity Trade And Finance

Authors: Michael Tamvakis

2nd Edition

041573245X, 978-0415732451

More Books

Students also viewed these Finance questions

Question

Differentiate sin(5x+2)

Answered: 1 week ago

Question

Compute the derivative f(x)=1/ax+bx

Answered: 1 week ago

Question

What is job enlargement ?

Answered: 1 week ago