Please show your working in excel or on paper. 18. While undertaking a project evaluation for an onshore wind park of 100MW, you have received
Please show your working in excel or on paper.
18. While undertaking a project evaluation for an onshore wind park of 100MW, you have received a production estimate of 3500 full load hours in the P-50 case. The lenders are testing the cash flows by means of the DSCR. The average DSCR by P99 should be 1.0x. Assuming the coefficient of variation for the production is 12%., what is the P-99 production (in GWh/year)? 321 252 2,525 296 447Step by Step Solution