Answered step by step
Verified Expert Solution
Question
1 Approved Answer
Please solve thanks!!! Q2 Change Order Question 15 Points For the activities shown in the table below, develop a plot that shows the Early, Late,
Please solve thanks!!!
Q2 Change Order Question 15 Points For the activities shown in the table below, develop a plot that shows the Early, Late, and Target S-Curves. Activity Duration Depends On $/Day Total $ A B Ola LO A A A C, D 2 17 3 5 6 2 1 $500 $200 $300 $100 $2,000 $500 $1,000 $1,000 $3,400 $900 $500 $12,000 $1,000 $1,000 Target Start 1 3 8 4 12 11 20 D B, E, F Q2.1 6 Points Please upload a pdf or image file of the S-Curves. Q2.2 6 Points Now, assume actual costs along with two change orders during the project as follows: Activity Depends On Actual Duration 2. 15 A B D CO#1 E F CO#2 G A A A D C, D D B B, E, F Actual $/Day $500 $250 $300 $100 $150 $2,000 $500 $300 $1,000 3 5 3 6 2 2 1 Actual Total $ $1,000 $3,750 $900 $500 $450 $12,000 $1,000 $600 $1,000 Actual Start 1 3 8 5 10 12 11 18 19 Based on the actual costs and change order data shown above, add the Actual S-Curve to the plots from Question 1. Please upload a pdf or image file. Q2.3 3 Points Also determine the total change order impact to the project. In other words, what is the total lost profit in the project's actual costs? (Hint: the lost profit is the movement from the slope in the original Target Curve vs. the Actual Curve)
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started