Answered step by step
Verified Expert Solution
Question
1 Approved Answer
Please solve this question. Using the following data to do the Earned Value analysis: calculate CV, SV, SPI and CPI per each period; BAC, EAC,
Please solve this question.
Using the following data to do the Earned Value analysis: calculate CV, SV, SPI and CPI per each period; BAC, EAC, ETC. Report whether the project at the end of September is under budget and on schedule or not. Implement formula calculations in Excel and construct EV, PV and AC cumulative graph, and a performance indices (SPI and CPI) graph. (10 points) Month PV AC EV May $120,000 $120,000 $120,000 June $192,000 $215,000 $170,000 July $192,000 $192,000 $173,000 $192,000 $216,500 $190,000 August September $192,000 $170,000 $185,000 October $60,000 Using the following data to do the Earned Value analysis: calculate CV, SV, SPI and CPI per each period; BAC, EAC, ETC. Report whether the project at the end of September is under budget and on schedule or not. Implement formula calculations in Excel and construct EV, PV and AC cumulative graph, and a performance indices (SPI and CPI) graph. (10 points) Month PV AC EV May $120,000 $120,000 $120,000 June $192,000 $215,000 $170,000 July $192,000 $192,000 $173,000 $192,000 $216,500 $190,000 August September $192,000 $170,000 $185,000 October $60,000Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started