Answered step by step
Verified Expert Solution
Link Copied!

Question

1 Approved Answer

Please type the correct option... I have had hard times reading some tutors handwriting or they do not follow the correct order. Thanks in advance

Please type the correct option... I have had hard times reading some tutors handwriting or they do not follow the correct order. Thanks in advance for making sure your selections are easy to read and following the correct order.

  1. An activity can include only one work package.
  • True
  • False

2)Experience suggests that when there are multiple starts, a common start node should be used to indicate a clear project beginning on the network. Similarly, a single project end node can be used to indicate a clear ending.

  • True
  • False

3)Which of the following represents an activity on an activity-on-node (AON) project network?

  • An arrow
  • A line
  • A node
  • Both an arrow and a line
  • An arrow, a line and a node all represent activities

4)Which of the following doesNOThelp describe a project network?

  • A graphic display of the flow and sequence of work through the project
  • Provides the basis for scheduling labor and equipment
  • Gives the times when activities can start and fini$h and when they can be delayed
  • Highlights major deliverables and identifies their completion dates
  • Identifies critical activities

5)The backward pass determines project duration.

  • True
  • False

6)The critical path is the shortest path through a network and indicates activities that cannot be delayed without delaying the project

  • True
  • False

7)An activity that has more than one dependency arrow flowing into it is termed a(n)parallel activity

  • critical path
  • burst activity
  • merge activity
  • independent activity

8)On a project network, the activity times are derived from the

  • organization breakdown structure
  • work packages
  • budget
  • project proposal
  • responsibility matrix

9)Information to develop a project network is collected from the

  • organization breakdown structure
  • work breakdown structure
  • Budget
  • project proposal
  • responsibility matrix

10)In developing a project network, neither looping nor conditional statements are permitted. In developing a project network, neither looping nor conditional statements are permitted.

  • True
  • False

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access with AI-Powered Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Managerial Accounting

Authors: Jennifer Cainas, Celina J. Jozsi, Kelly Richmond Pope

1st Edition

0137689454, 9780137689453

Students also viewed these General Management questions

Question

Define line and staff authority

Answered: 1 week ago

Question

Define the process of communication

Answered: 1 week ago

Question

Explain the importance of effective communication

Answered: 1 week ago

Question

* What is the importance of soil testing in civil engineering?

Answered: 1 week ago